Handle a Project Scope Change: Compare Three Options

By BestTools ·

Record the current scope, fee and estimated effort first. Then compare adding the requested work for an explicit extra fee, excluding a named original task, or retaining the request for a later discussion. None of these options is agreed until you confirm it with the client.

Open Project Change Planner →

Record the request before choosing an option

  1. Record the original fee and total estimated hours, including the existing work you may remove.
  2. Name the requested work and estimate its hours. State the extra fee you would propose for the Add option, including zero if that is deliberate.
  3. For Swap, name an in-scope task to exclude and its estimated hours. Do not remove more hours than the original total.
  4. Record a scope version and source or discussion notes. Missing notes remain unverified.
  5. Compare the options, edit the discussion drafts and confirm scope, fee and timing with your client before changing the work.

Download the original synthetic plan JSON ↓

Work through a fixed-price example

This synthetic project has an original fee of USD 2,000 and an estimate of 20 hours. A booking request form adds an estimated 5 hours. The proposed Add fee is USD 500. The original fee divided by estimated effort is USD 100/h. This is a revenue reference, not profit or a recommended hourly rate.

OptionCurrent feeCurrent estimated effortWhat stays explicit
Add and chargeUSD 2,50025 hUSD 500 is a proposed extra fee, pending confirmation
Swap a named 5 h FAQ pageUSD 2,00020 hFAQ page is excluded; equal hours do not prove equal value
Swap a named 3 h taskUSD 2,00022 hTwo additional hours remain at the same fee
Defer the formUSD 2,00020 hRequest is retained; later price and timing are undecided

Check the assumptions that can change the decision

If the added fee is zero, Add becomes USD 2,000 / 25 h = USD 80/h: 20% below the original revenue-per-estimated-hour reference. It does not establish a profit loss. Costs, taxes, overhead and the reliability of your effort estimate still matter.

If you exclude an 8 h task and include 5 h of new work, the new total is 17 h. The planner shows 3 h released and keeps the original fee; it does not invent a refund. If you exclude only 3 h, it shows 2 h of extra effort rather than calling the exchange equal.

Without a named task and positive removed hours, Swap stays incomplete while Add and Defer can still be compared. Zero original hours is invalid because the reference rate would be undefined. A zero original fee is allowed but cannot provide a useful percentage reference.

No calendar dates are calculated. Timing notes are text, not promises. Different tasks can carry different uncertainty even when their hour estimates match.

Keep an editable record without treating it as approval

Edit the client discussion text for each option. If you change inputs and compare again, edited drafts are kept, so check them against the revised figures or regenerate them.

Download JSON to continue editing in this tool. Standalone HTML is a readable snapshot with no scripts or external assets. Imports accept the versioned plan format, not arbitrary project files. Keep downloaded client information private as appropriate.

The planner keeps inputs in tab memory and does not upload project content. Ordinary hosting requests still occur when the site loads. Reset or a fresh reload clears the working state; downloads remain on your device.

A discussion draft is not consent, an invoice, a signature, contract interpretation or legal advice. This tool does not decide whether a request is in scope and does not send anything to a client. FWD offers a change-request log; Scope Assistant is another scope-planning alternative. Compare existing workflows before assuming a new tool saves time.